CORE COMPETENCIES
• Claim Management
• BOQ
• Cost Control
• Project Control
• Clients Invoicing
• Subcontractors Payments Certificates
• Estimation
• Cost Reports / Progress Reports
PROFESSIONAL EXPERIENCE
NOV 2013 – JUL 2019
QUANTITY SURVEYOR – CIVIL
CONSOLIDATED CONTRACTORS CO (CCC) – AS PART OF THE BACS CONSORTIUM
RIYADH, SAUDI ARABIA.
Department: Project Control
Reporting to: PM (Utilities Diversion: (Samer Mokaddem)
Project: Riyadh Metro Project Package 1
Contract Value: USD 10 Billion approx.
Achievements:
Unforeseen Claims Team
• Provided support for successful defense of Unforeseen Utilities Claim worth over US $100 Million.
• Identification & Quantification of Unforeseen Wet & Dry Utilities
for Claim.
• Backup Unforeseen Claims for Client’s Verification
• Maintain Unforeseen Claims Correspondence log
Utilities Diversion Team
• Quantities Take Off / BOQ for Budget / Forecasts
• Work Progress Monitoring / QURR Weekly Reports
OCT 2011 – MAY 2013
QUANTITY SURVEYOR – CIVIL
AL HASSAN ENGINEERING CO
ABU DHABI, UAE.
Department: Planning & Cost Control
Reporting to: Planning & Cost Control Manager (Nagendra Kumar Chaurasiya)
Projects:
• Asab III NGL Gas Plant at Asab, Abu Dhabi, UAE.
• Oil Terminal at Hamriya FZ, Sharjah, UAE.
• Oil Tank Farm at Hamriya FZ, Sharjah, UAE.
• 400/220/33KV Grid Substation (BAB II) at Bab, Abu Dhabi, UAE.
Contract Value: USD 8 - 35 Million
Achievements:
Asab III Gas Plant
• Valuation for Client Invoicing & Monthly Financial Status Report –
MFSR.
• Variations – Deriving and getting approved the rates, Calculating
the quantities and amount.
• Contract Closeout – Calculations to get the Final Value of the
works as specified in the Contract.
Oil Terminal at Hamriya FZ
• Monthly Valuation for Client Invoicing
Oil Tank Farm at Hamriya FZ
• Studying Bid Documents, raising queries and getting clarifications
• Quantities Take Off, BOQ & Estimation
400/220/33KV Grid Substation (BAB II)
• Preparing BOQ
FEB 2010 – APR 2011
SENIOR COST CONTROLLER
SAUDI OGER LTD
RIYADH, SAUDI ARABIA.
Department: Cost Control
Reporting to: Cost Control Manager (Christophe Dekeuster)
Project: Princess Noura University for Women, Riyadh, Saudi Arabia.
Contract Value: USD 3.19 Billion
Achievements: –
External Works Package (Budget: USD 117 Million)
• Supervised a team of 2 Cost Controllers & 2 Data Entry clerks
• Issue Cost Reports / Productivity Reports
• Manpower Daily Reports
SEP 2008 – FEB 2009
QUANTITY SURVEYOR
AL FUTTAIM CARILLION LLC
DUBAI, UAE.
Department: Quantity Surveying
Reporting to: Commercial Manager (Kirk Douglas)
Project: Central Boulevard Towers at Dubai, UAE.
Achievements:
• Checking Contractors / Vendors Bills and preparing Payment
Certificates
JUL 1995 – SEP 2008
QUANTITY SURVEYOR / BILLING ENGINEER / SR BILLING ENGINEER
FIT OUTS CONTRACTORS / REAL ESTATE DEVELOPERS
MUMBAI, INDIA.
EDUCATION
DIPLOMA IN CONSTRUCTION ENGINEERING
BOARD OF TECHNICAL EDUCATION, MAHARASHTRA STATE, INDIA.
JULY 1995
CERTIFICATION
ADVANCED COURSE IN QUANTITY SURVEYING (ACQS)
ROYAL INSTITUTE OF CHARTERED SURVEYORS (RICS)
OCTOBER 2014
PERSONAL DETAILS
• DOB – 2nd May 1970
• Nationality – Indian
• Driving License – Saudi LV
SOFTWARE SKILLS
• MS Office
• AutoCAD
• ERP
TRAINING
• FIDIC Contracts
• Projectwise
• Acconex
• ERP
RECOMMENDATIONS :-
"Enabling Works Team:
Rizwan has joined the Riyadh Metro Project in November 2013 as part of the Enabling Works Team.
The Enabling Works Team overlooked several scopes of works ranging from Mobilization, Utilities Diversion, Road Works and At Grade Works to which Rizwan was tasked to overlook.
Rizwan was mainly tasked with the Utilities Diversion works and has shown the following key strengths:
In depth knowledge of the Contract Volumes related to Utilities Diversion works for both Wet and Dry.
Accurate quantification of the works.
Identification of works outside of Contract (Unforeseen Utilities).
Strong technical background.
Great team player.
Copes well under pressure.
Unforeseen Utilities Claim Team:
A team was tasked to identify, quantify and estimate utilities deemed as Unforeseen (Encountered on site, however not shown on the Contract drawings).
Rizwan has identified and quantified over US $100M worth of utilities (wet and dry) that are considered as Unforeseen.
He is a proactive team player, who worked closely with the site teams to ensure all unforeseen utilities are accounted for in the Claim."
Anthony Sarkis
Assistant Director at
Almabani General
Contractors
"Rizwan is a motivated and hardworking colleague whom consistently demonstrated solid work and focus. We worked on Direct cost claims for almost two years in a mega project which required team players such as himself and commitment to meet deadlines.
I strongly recommend Rizwan as I’m confident he will be an invaluable addition to any team"
Amro Baassiri
Handover Lead |
Claims Specialist at
Almabani General
Contractors
"worked together for a project from 2011 to 2013 at Abhu Dhabi for Asab-3 Project where Rizwan was employed for one of our Subcontractors. He was a fine, polite and knowledgeable Quantity Surveyor to deal with.
I wish him prosperity in his career"
Ramanathan V H
Subcontracts
Engineer at Technip