Career Summary

DIPLOMA OF MECHANICAL with 12 years experience in -Select- functional area

Skill Set

PIPING AND WELDING INSPECTION,NDT INSPECTION,HYDRO TESTING INSPECTION,

Professional Information

Total Experience : 12

Nationality : Pakistan

Qualification Level : ITI / Vocational

Job Function : Quality / Testing

Work Location Preference : Kuwait, Bahrain, Oman, Saudi Arabia, Qatar, UAE

Detailed Profile

QAISIR MEHMOOD
MECHANICAL INSPECTOR
INTERTEK SAUDI ARABIA
12 YEAR EXPERIENCE

ACADEMIC QUALIFICATION

B-Tech (Mechanical) from Preston University Karachi Pakistan in 2010

Diploma of Associate Engineer (DAE- Mechanical) from Punjab Board of Technical Education, Lahore in 2007

CERTIFICATION
API 510 Vessel Inspector
API 570 Piping Inspector
API 653 Tank Inspector
CSWIP 3.2.2 Welding Inspector
NDT Level II(RT,MT,PT,VT,UT)
LEEN SIX SIGMA(GREEN BELT)
Aramco SAP# 80006073:
CBT PASS=WELDING & PIPING & ROTATING & STATIC EQUIPMENT.


CONTACT DETAILS

E-Mail:qaisir.insp@hotmail.com
Contact:00966581372544
Contact:00923350517989

PERSONAL DETAILS

Date of Birth: 18th August 1988
Languages Known: English
Driving License: UAE/KSA Nationality: Pakistani
Passport No.: MP 0154902
Marital Status: Married
Present Address: HARAD
General inspection responsibility.
• Responsible for quality monitoring for all stages of the project cycle from design review up to the approval of Final MCC to ensure compliance with applicable Mandatory Saudi Aramco Engineering Requirement and project specifications.
• Monitor and inspect ongoing construction activities. This is to ensure that rework and potential non-compliances are avoided.
• Surveillance results whether they are Violations, Pro-active Notifications, or No Findings shall be logged in the QMIS under General Comments.
• Review the quality control documents including the Inspection and Test Plan (ITP), prior to the start of any construction or pre-commissioning activity, in accordance with Schedule Q and test results for conformance to project requirements.
• Ensure that the QC Procedures and associated ITPs for Material Receiving, Storage, Traceability, and Preservation are approved prior to the start of material receiving activities.
• Inspect major equipment (e.g., fired and unfired vessels, skid-mounted equipment, pumps, compressors, etc.), and perform random inspections of bulk construction material for compliance with standards, codes, and specifications, and for possible damage during shipping, handling, and installation.
• Check for the availability of the Supplier inspection release, inspection records, and recommendations for storage and preservation at the time of receipt.

Stationary & Rotatory Equipment Inspection
• Preservation Monitoring of Vessel, Tanks, Pumps, Compressor, and Air-cooled Heat Exchangers.
• Installation of the compressor, Fin Fan, and pumps.
• Installation of Static Equipment.
• Pre-Alignment and Final Alignment of Rotating Equipment.
• Internal inspection of Static Equipment.
• Inspection of Atmospheric Storage Tanks Fabrication, Erection, and Testing as per API 650.
• Understanding requirements of internal & external inspection of pressure vessels, drums, heat exchangers, storage tanks, columns, furnaces, boilers, flares, plant piping & refractory
• Reviewing the documents prior to release for hydro/Pneumatic testing and witnessing the tests, hydrostatic and pneumatic leaks testing.
• Knowledge of failure mechanism for corrosion and, erosion, damages, cracks, pits, thinning, or other failures found during plant shut down/equipment downtime.
• Monitoring of Oil flushing, chemical Cleaning, and Mechanical Cleaning of Piping.
• Review the Box Up packages and offer for inspection to the proponent for final closure.

Welding & Piping Inspection

• Review the WPS and PQR as per construction codes ASME Sec.IX, ASME B 31.3, ASME Sec. VIII.
• Monitoring of welding parameters during procedure qualification testing & witnessing welder qualification tests.
• Review the fabrication procedure, erection sequence, quality procedure, inspection method, reading drawing isometric, GAD, P&ID.
• Handling the mechanical (Tensile, Bend, Charpy), hydro testing, welder qualification test, witness hydro test, thermal treatment of material preheating, stress reliving, inter-pass temperature & post heat treatment witness ..
• Inspecting the incoming materials for damages, dimensions, and corrosions and ensuring that Material Test Certificate is available and according to the requirements.
• Managing preliminary welding inspection activities (fit-up, root pass, intermediate, and hot pass, materials traceability, dimensional checking, and orientations of piping components).
• Handling internal inspection of fit-up, welding of the pipeline, and joint check-up of the piping using P&ID and Isometric Drawings.
• Inspection and monitoring of Welding Consumable Control (Receiving, Storage, Handling, Issue & Conditioning).
• Carrying out visual inspection of weld joints after welding and selection of NDT, PWHT, Hardness Ferrite, and PMI testing as per line class.
• Selection and monitoring of NDT activities as per approved procedures and standards.
• Carrying out visual inspection of piping to see any rust/corrosion and also the condition of pipe supports.
• Updating & maintaining the calibrations status for all instruments.
• Review the Hydrotest package and verify the Pre-Test Punch listing.
• After Hydrotesting verification of Re-Instatement and layup.
• Raising the NCR for the concerned department that’s going against the QAP, approved work procedure, quality & system, international standard, and Aramco Standards.